Construction of the Inuvik to Tuktoyaktuk Highway, Northwest Territories

Phases

Each phase card reflects where this project stands in the six-phase Environmental Impact Review process. The current phase is highlighted automatically. Select any phase to explore its timeline and key activities in detail.

Timeline

Milestone / Task
APR
MAY
JUN
JUL
AUG
Receipt of EISC referral
Additional information requests
Internal consultation on referral
Prepare internal information package
Q and A on EIRB process and procedures
Planning preliminary steps for the Review
Engage external review assistance
Parties register, establish broad schedule
EIRB meeting
Communications with Developer and Canadian Environmental Assessment Agency
Prepare and submit review budget to INAC
Review track decision
Prepare RFP for Technical experts; 2-week proposal call; choose and retain technical experts

Details

Phase 1 — Initiation