Construction of the Inuvik to Tuktoyaktuk Highway, Northwest Territories

Phases

Each phase card reflects where this project stands in the six-phase Environmental Impact Review process. The current phase is highlighted automatically. Select any phase to explore its timeline and key activities in detail.

Timeline

Milestone / Task
OCT
NOV
DEC
JAN
FEB
MAR
APR
90 days for Developer to respond to ToRs with draft EIS
Receive draft EIS; all Party conformity review
Conformity deficiency letter sent to Developer
Developer given 45 days to respond to conformity deficiency letter
Accept EIS as Final; Appoint Review Panel

Details

Phase 3 — EIS Development